<witsml:presTestType>leak off test</witsml:presTestType>
<witsml:distDrilluom="m">78.9</witsml:distDrill>
<witsml:elevKellyuom="m">23.5</witsml:elevKelly>
<witsml:waterDepthuom="m">15</witsml:waterDepth>
<witsml:sum24Hr>Circulate and condition hole at 6154m. Resume drilling 8-1/2" production hole section from 6154m to 6162m. Continue to circulate and condition hole to remove cuttings from hole and attempt to reduce loss rate. Resume drilling 8-1/2" production hole section from 6162m to 6292m. Losses ranging from 6 m3/hr to 19 m3/hr while drilling and circulating.</witsml:sum24Hr>
<witsml:forecast24Hr>Continue to drill 8-1/2" production hole section to TD. Circulate and condition hole.</witsml:forecast24Hr>
<witsml:comments>Continue drilling 8-1/2" production hole section. Reduce RPM to 80 and increase pump rate to 1850 lpm to send downlink. Resume drilling f/ 6154m to 6162m. 1600 lpm, 180 bar, 31-33 kNm drilling torque, 3-4 ton WOB. Losses while drilling from 8 m3/hr to 12,2m3/hr