DrillReport_23.03.2011.xml 8.61 KB
<?xml version="1.0" encoding="UTF-8"?>
<drillReports xmlns="http://www.witsml.org/schemas/1series" version="1.4.0.0">
<drillReport>
<nameWell>2/1-A-25</nameWell>
<nameWellbore>A-25 A</nameWellbore>
<name>2/1-A-25</name>
<dTimStart>2011-03-23T00:00:00.000Z</dTimStart>
<dTimEnd>2011-03-24T00:00:00.000Z</dTimEnd>
<versionKind>normal</versionKind>
<createDate>2011-03-24T07:04:05.550Z</createDate>
<wellAlias>
<name>0</name>
<namingSystem>NPD code</namingSystem>
</wellAlias>
<wellboreAlias>
<name>2/1-A-25 A</name>
<namingSystem>NPD code</namingSystem>
</wellboreAlias>
<wellboreAlias>
<name>6482</name>
<namingSystem>NPD number</namingSystem>
</wellboreAlias>
<wellboreInfo>
<dTimPreSpud>2011-01-27T13:00:00.000Z</dTimPreSpud>
<operator>Talisman Energy Norge</operator>
<drillContractor>Archer</drillContractor>
<rigAlias>
<name>Gyda</name>
<namingSystem>NPD Name</namingSystem>
</rigAlias>
<rigAlias>
<name>272337</name>
<namingSystem>NPD code</namingSystem>
</rigAlias>
</wellboreInfo>
<statusInfo>
<dTim>2011-03-23T00:00:00.000Z</dTim>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">3089.0</md>
<tvd datum="ff8080812d82ea35012dbcc14fac200b" uom="m">2440.23</tvd>
<diaHole uom="in">17.5</diaHole>
<mdDiaHoleStart datum="ff8080812d82ea35012dbcc14fac200b" uom="m">65.5</mdDiaHoleStart>
<diaPilot uom="in">0.0</diaPilot>
<typeWellbore>initial</typeWellbore>
<diaCsgLast uom="in">13.375</diaCsgLast>
<mdCsgLast datum="ff8080812d82ea35012dbcc14fac200b" uom="m">3081.4</mdCsgLast>
<tvdCsgLast datum="ff8080812d82ea35012dbcc14fac200b" uom="m">2435.4</tvdCsgLast>
<sum24Hr>Installed outer and Inner FOG on A-25. Skidded rig from Slot 32 to slot 25. Nippled up HP riser on slot 25 . Nippled up 13 5/8" BOP. Moved 21 1/4" BOP to be stored on slot 28.</sum24Hr>
<forecast24Hr>N/U 13 5/8" low pressure riser and diverter. Pressure test BOP to 200 bar.</forecast24Hr>
</statusInfo>
<fluid>
<type>ENVIROMUL</type>
<dTim>2011-03-23T15:00:00.000Z</dTim>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">905.0</md>
<presBopRating uom="bar">200.00000000000006</presBopRating>
<mudClass>oil based</mudClass>
<density uom="g/cm3">1.549994265</density>
<pv uom="mPa.s">47.0</pv>
<yp uom="Pa">13.4</yp>
</fluid>
<activity>
<dTimStart>2011-03-23T00:00:00.000Z</dTimStart>
<dTimEnd>2011-03-23T02:30:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Installed Outer &amp; Inner FOGs on A-32. Outer FOG installed and landed in frame on BOP deck by use of tugger and North crane. Inner FOG installed with tugger from drill floor.</comments>
</activity>
<activity>
<dTimStart>2011-03-23T02:30:00.000Z</dTimStart>
<dTimEnd>2011-03-23T04:00:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Disconnected HP riser from A-32 wellhead. Connected 10 ton slings from DDM to HP riser and lifted riser to BOP deck. Laid down HP riser to BOP deck with DDM &amp; North Crane.</comments>
</activity>
<activity>
<dTimStart>2011-03-23T04:00:00.000Z</dTimStart>
<dTimEnd>2011-03-23T06:00:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Removed Inner and Outer FOGs from A-32 and positioned on BOP deck. Moved aside BOP hatch from A-25 and lifted FOG frame from A-32 to A-25. Moved scaffolding from A-32 to A-25. Installed Outer &amp; Inner FOGs on A-25.

</comments>
</activity>
<activity>
<dTimStart>2011-03-23T06:00:00.000Z</dTimStart>
<dTimEnd>2011-03-23T08:30:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Preparing for skidding rig from A-32 to A-25.</comments>
</activity>
<activity>
<dTimStart>2011-03-23T08:30:00.000Z</dTimStart>
<dTimEnd>2011-03-23T09:00:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Performed pre-job meeting prior to start skid from slot 32 to slot 25</comments>
</activity>
<activity>
<dTimStart>2011-03-23T09:00:00.000Z</dTimStart>
<dTimEnd>2011-03-23T10:00:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Skidded rig from slot 32 to slot 25. </comments>
</activity>
<activity>
<dTimStart>2011-03-23T10:00:00.000Z</dTimStart>
<dTimEnd>2011-03-23T13:30:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Rig on location on slot 25. Secured rig according to compass procedures.</comments>
</activity>
<activity>
<dTimStart>2011-03-23T13:30:00.000Z</dTimStart>
<dTimEnd>2011-03-23T14:00:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Performed pre-job meeting prior to start nippling up HP-riser and BOP on A-25.</comments>
</activity>
<activity>
<dTimStart>2011-03-23T14:00:00.000Z</dTimStart>
<dTimEnd>2011-03-23T14:30:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Build scaffolding to secure around open hatch on diverter deck. </comments>
</activity>
<activity>
<dTimStart>2011-03-23T14:30:00.000Z</dTimStart>
<dTimEnd>2011-03-23T16:30:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Nippled up HP riser on A-25 well head.  </comments>
</activity>
<activity>
<dTimStart>2011-03-23T16:30:00.000Z</dTimStart>
<dTimEnd>2011-03-23T19:30:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Installed 13 5/8" BOP on HP-riser and made up fast lock connector. </comments>
</activity>
<activity>
<dTimStart>2011-03-23T19:30:00.000Z</dTimStart>
<dTimEnd>2011-03-23T21:00:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Moved 21 1/4" BOP to slot 28 on BOP deck for storage. 

Meanwhile: cleaned and tidied on rig floor. And troubleshot on DDM tilt link.
</comments>
</activity>
<activity>
<dTimStart>2011-03-23T21:00:00.000Z</dTimStart>
<dTimEnd>2011-03-23T23:00:00.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Turned Kill and choke outlets on BOP to install kill and choke hoses. Lifted down kill and choke hoses from drill floor to BOP deck and installed same. 

Meanwhile: Changed out slide in link tilt operating valve - Link tilt working properly </comments>
</activity>
<activity>
<dTimStart>2011-03-23T23:00:00.000Z</dTimStart>
<dTimEnd>2011-03-23T23:59:59.000Z</dTimEnd>
<md datum="ff8080812d82ea35012dbcc14fac200b" uom="m">0.0</md>
<phase>fixed</phase>
<proprietaryCode>drilling -- bop/wellhead equipment</proprietaryCode>
<state>ok</state>
<stateDetailActivity>success</stateDetailActivity>
<comments>Installed master bushing in rotary. Performed pre-job meeting prior to lifting in LP-riser.  Picked up LP-riser and installed same in RKB. </comments>
</activity>
</drillReport>
</drillReports>