Tore Christiansen

Added dates to Scheduled Activity 1

Showing 1 changed file with 21 additions and 1 deletions
......@@ -515,7 +515,27 @@ ILAP:ScheduledActivity_1
rdf:type ILAP:ScheduledActivity ;
rdfs:label "Scheduled activity 1"^^xsd:string ;
ILAP:hasActivityCalendar
ILAP:Calendar_1 .
ILAP:Calendar_1 ;
ILAP:hasBaselineActivityDuration
"P0Y6M05D"^^xsd:duration ;
ILAP:hasCurrentActivityDuration
"P0Y6M15D"^^xsd:duration ;
ILAP:hasEarlyFinish "2015-06-16"^^xsd:date ;
ILAP:hasEarlyStart "2015-01-02"^^xsd:date ;
ILAP:hasEarlyStartActual
"2015-01-05"^^xsd:date ;
ILAP:hasFixedFinish "2015-07-05"^^xsd:date ;
ILAP:hasFixedStart "2015-01-05"^^xsd:date ;
ILAP:hasLateFinish "2015-08-01"^^xsd:date ;
ILAP:hasLateStart "2015-01-15"^^xsd:date ;
ILAP:hasOriginalActivityDuration
"P0Y6M0D"^^xsd:duration ;
ILAP:hasRemainingActivityDuration
"P0Y2M15D"^^xsd:duration ;
ILAP:hasScheduleDate
"2015-01-05"^^xsd:string ;
ILAP:hasScheduledFinish
"2015-07-01"^^xsd:date .
ILAP:ScheduledActivity_2
rdf:type ILAP:ScheduledActivity ;
......