Håvard M. Ottestad

activities need to be able to have multiple schedules. Eg. a live schedule, baseline schedule....

......@@ -93,12 +93,6 @@ userfield:hasFreeFieldForSpecifiedUserField
] ;
rdfs:subClassOf [
rdf:type owl:Restriction ;
owl:maxQualifiedCardinality "1"^^xsd:nonNegativeInteger ;
owl:onClass :ScheduleForActivityInPlan ;
owl:onProperty :hasSchedule ;
] ;
rdfs:subClassOf [
rdf:type owl:Restriction ;
owl:minQualifiedCardinality "0"^^xsd:nonNegativeInteger ;
owl:onClass :CompletelyFreeField ;
owl:onProperty :hasCompletelyFreeField ;
......@@ -130,6 +124,12 @@ userfield:hasFreeFieldForSpecifiedUserField
rdfs:subClassOf [
rdf:type owl:Restriction ;
owl:minQualifiedCardinality "0"^^xsd:nonNegativeInteger ;
owl:onClass :ScheduleForActivityInPlan ;
owl:onProperty :hasSchedule ;
] ;
rdfs:subClassOf [
rdf:type owl:Restriction ;
owl:minQualifiedCardinality "0"^^xsd:nonNegativeInteger ;
owl:onClass :Status ;
owl:onProperty :hasActiveStatus ;
] ;
......