rdfs:label"Activity Role for Rosenberg to ConocoPhillips 2.0"^^xsd:string;
USERFIELDS:hasShort"Activities to specify objects and produce basic for modelling, Mhr. Carrier"^^xsd:string,"Control object progress, Jobs"^^xsd:string,"Modelling activities containing objects to be both engineered and modelled, Mhr. Carrier"^^xsd:string,"Jobs in KIFS, Manual progress"^^xsd:string,"Control object progress"^^xsd:string,"Job progress"^^xsd:string,"Manual progress"^^xsd:string,"Manual progress, Mhr Carrier"^^xsd:string,"Document progress"^^xsd:string,"Modelling activities containing objects to be modelled only, not engineered, Mhr. Carrier"^^xsd:string,"Document, Manual progres"^^xsd:string,"Doc. prg, Mhr. Carrier"^^xsd:string,"Control object manula progress"^^xsd:string,"Mhr. Carrier"^^xsd:string,"Procurement Milestone"^^xsd:string,"Doc. prg, jobs"^^xsd:string.
ILAP:ActivityWBS_1
rdf:typeILAP:ActivityWBS;
rdfs:label"Activity WBS 1"^^xsd:string;
ILAP:hasWBScomponent
SCCS:PBS_ACAA,ILAP:PBS_ACAA_1;
ILAP:hasWBSphaseSCCS:SAB_51,ILAP:SAB_51_1;
ILAP:hasWBSresourceSCCS:COR_KD,ILAP:COR_KD_1.
ILAP:PBS_ACAA_1,SCCS:PBS_ACAA;
ILAP:hasWBSphaseILAP:SAB_51_1,SCCS:SAB_51;
ILAP:hasWBSresourceILAP:COR_KD_1,SCCS:COR_KD.
ILAP:AreaCode
rdf:typeUSERFIELDS:FreeTextField;
rdfs:label"Area Code for Rosenberg to ConocoPhillips 2.0"^^xsd:string;
rdfs:label"Buiding Block for Rosenberg to ConocoPhillips 2.0"^^xsd:string;
USERFIELDS:hasDescription
"Modifications of GI ducting system to WHRU"^^xsd:string;
USERFIELDS:hasShort"D1"^^xsd:string.
"Onshore fabrication and assembly of a new WHRU module"^^xsd:string,"Demolition of old WHRU module"^^xsd:string,"Hook-up of tie-in and integrating of new WHRU"^^xsd:string,"Modifications of GI ducting system to WHRU"^^xsd:string,"Manhours needed for delivery of SOW, but not invoiced to Company"^^xsd:string,"LP Hydro Cyclone"^^xsd:string,"Installation of temp. generator for stable power supply"^^xsd:string,"ELDF Assist (E- 040)"^^xsd:string,"Modifications of WI ducting and vertical exhaust stacks to WHRU"^^xsd:string,"X-Over"^^xsd:string,"Demolition Gas Lift Compressor"^^xsd:string,"Gas Lift Compressor"^^xsd:string,"Prep. Of tie-in and integrating work for new WHRU"^^xsd:string,"General, for general work activities, not specifically allocated to one of the following Building Blocks (W1, W2,W3, W4, W5, D1 or D2)"^^xsd:string,"Assistance to COPSAS Comm"^^xsd:string,"Contract General Milestones"^^xsd:string;